"The best way negotiation works is everyone walks away a little bit unhappy." Commissioner George Kruse said that on Oct. 20, just before the Manatee County Commission voted 5-1 to let the Cortez Bridge contractor use the former Seafood Shack property as its staging area, as the AMI Sun reported.
His line describes the next four years in Cortez well. The Florida Department of Transportation's $123 million replacement of the bridge on State Road 684 covers about 0.9 miles of bridge and approaches, from Gulf Drive to 123rd Street West. FDOT senior projects engineer Dustin Spears gave Nov. 9 as the tentative start date, with the first visible work happening on the water. The contractor's staging area will be land the county bought in 2024 for $13 million, and that choice decides who absorbs the construction.
What the license agreement settled
The deal gives SEMA Construction the former Seafood Shack property for four years. The site is split into two working areas. Parcel 1, at the south end, will hold semi-permanent structures, including a crane access trestle. Parcel 2 sits along the water north of the humpback bridge on 127th Street West. SEMA representative Justin Oakes told commissioners it would serve mainly as overflow parking for employees and as a place to handle and store materials, and that crews would assemble forms and rebar cages there and load them straight onto barges. The area will be fenced, gated and posted to keep the public out.
Oakes said the project will need more than 3,000 truckloads over its 1,200-day contract period, which averages three to five truckloads a day. Without Parcel 2, he said, the contractor would have relied heavily on the state-owned right-of-way in front of Tide Tables, and that would have meant daily lane closures on Cortez Road.
Each party gains something and gives something up:
| Party | What the agreement keeps or gains | What it gives up |
|---|---|---|
| Cortez Road drivers | Staging moves off the state right-of-way, so the case for daily lane closures goes away | Intermittent lane closures can still happen at any time of day |
| Tide Tables | Its customer parking lot stays out of construction staging | The restaurant sits beside an active bridge site until late 2029 |
| Neighborhoods north of the bridge | Nothing that the July discussions had not already offered | A fenced material assembly yard beside their road to Cortez Road |
| Manatee County | SEMA drops claims for delay costs the county estimated at about $1.4 million, and builds a ferry dock | The waterfront it bought in 2024 is off-limits to the public for four years |
| SEMA Construction | A staging area right next to the bridge | Obligations to build the county's ferry facilities and remove a house on the site |
The $1.4 million figure comes from a county delay. Manatee County Utilities Chief Engineer Chad Butzow told commissioners that the county's project to install a new water main under the Intracoastal Waterway is well behind schedule. The old main conflicts with pilings SEMA has to drive for the bridge's first stage, which was supposed to begin in June. In return for using the land, SEMA agreed not to seek delay costs from the county or the state. The county's background materials gave the traffic reasoning plainly: an adjacent staging area "reduces the need for large construction vehicles and equipment to repeatedly back into or out of the constrained FDOT right-of-way."
Why the restaurant's parking lot mattered to everyone on Cortez Road
Tide Tables co-owners Karen Bell and Bobby Woodson told commissioners that staging construction in the right-of-way in front of their restaurant would nearly put them out of business by taking away its parking. Woodson said the restaurant employs about 50 people and serves 500 to 1,000 customers a day. He also said more lane closures would back traffic up to 75th Street during the busy spring season. Both owners supported the agreement.
Joe Adorno, president of Cortez Park Homeowners Inc., which owns both the Cortez Park mobile home community and the neighboring Tide Tables property, said the restaurant is a major source of income for the association. He also said trucks and construction equipment cannot share the restaurant's driveway without disrupting it.
So one parking lot connects a restaurant's business, a homeowners association's income and the backup on Cortez Road in March. Kruse put it in traffic terms. Turning SEMA down would push the work into the restaurant's parking area, which could bring lane closures and long backups.
The households on the other side of the humpback bridge
The cost moves to the neighborhoods north of the bridge. The plan presented to the commission in June described Parcel 2 as overflow parking for construction workers. Residents who spoke on Oct. 20 said they met with planners and SEMA representatives on July 10, were told Parcel 2 would hold only light-vehicle parking, and agreed to that. They said they learned only days before the vote, from documents posted online, that the site map had been relabeled to include "contractor material assembly staging and parking."
One resident told the commission that more than 300 residents pass the Parcel 2 area to enter and leave their neighborhoods, which have one way in and one way out to Cortez Road. Butzow acknowledged he had overlooked a July email from a neighborhood group that objected to any use of the land north of the bridge. Oakes said SEMA did not intend to mislead anyone. Commissioner Jason Bearden, who cast the only vote against the agreement, said his concern was transparency and that a compromise might have been possible if the change had been discussed with residents earlier.
Under the Phase 1 schedule, that same corner gets a new road. FDOT's plans include Hunters Point Way, which connects Cortez Road to 127th Street West and gives access to Tide Tables on the south side of Cortez Road. Once it opens, 127th Street West is expected to close temporarily, with traffic detoured onto the new road.
The order of changes, as currently scheduled
FDOT calls this schedule tentative and subject to change. Here is the sequence presented at the Oct. 20 public information session at Kirkwood Church on Cortez Road West:
- This fall. Crews start on the north side of the existing bridge at its east end, building a temporary trestle and driving pilings one pier at a time. The south sidewalk closes, and pedestrians are detoured to the north side. Crews also build Hunters Point Way, a stormwater pond, Manatee County sewer work and the first seawalls.
- Early 2027. Traffic moves onto a temporary diversion roadway, construction begins on the north side of Cortez Road, Hunters Point Way opens, and installation of a county water main begins.
- Spring 2027. 127th Street West is expected to close temporarily, with traffic detoured via Hunters Point Way. Phase 1 ends after this stage.
- Spring 2028. Phase 2 begins. Traffic shifts onto the new bridge, and demolition of the existing bridge starts.
- Summer 2029. The whole bridge is expected to open to traffic, with final paving. Punch-list work runs into late 2029.
Throughout all five stages, Cortez Road is not expected to close completely. Spears said individual lane closures will happen intermittently and "can happen any time during the day." When the work is done, the fixed-span bridge is designed with 65 feet of vertical clearance for boat traffic, according to the AMI Sun's Oct. 14 preview of the session. FDOT's design-phase Bridge Aesthetics Committee, which included members from Cortez and Bradenton Beach, preferred four overlooks on the north and south sides at the piers on either side of the main channel, lighting on the pier columns, and a custom "wave" pattern in the pedestrian railings. FDOT notes these preferences may change in final design.
The waterfront that waits
The third party absorbing the cost is the Seafood Shack site's own future. When Manatee County bought the property in 2024, the stated plan was a public boat launch and marina. Since then, county discussions have turned toward a park and possibly a Gulf Islands Ferry stop.
The license agreement moves one of those plans forward. It requires SEMA to build a docking, storage and fueling area for the county's Gulf Islands Ferry service and to demolish and remove a house on the property. Plans for public use of the rest of the land wait until the staging period ends.
Some people in Cortez are using that wait. At the July 6 meeting of the Florida Institute of Saltwater Heritage, as the AMI Sun reported, Cortez Village Historical Society Vice President Paul Dreyfoos proposed forming a brainstorming group to draft guiding principles for the site. He framed it as an eco-park, with ideas including a canoe launch, boat ramp access for commercial fishers, boat-to-table food service and environmental education for boaters. "It pushes the planning cycle way down the road," he said of the bridge work. FISH board member David Cadmus said the delay "could give us some time and work in our favor."
Keeping up with the work
FDOT posts project updates and an email sign-up on its Cortez Bridge project page. Construction project manager Juan Carrillo is listed there at (941) 708-4446 and [email protected]. For the latest on the Seafood Shack site, the commission vote and the July 10 resident meeting, the AMI Sun's coverage of the staging agreement and its report from the FDOT information session are the most complete accounts.
Four years of bridge work along Cortez Road changes daily routes, timing and access for the homes and businesses on both approaches. If you own property near the bridge or along the corridor and want to think through how this schedule fits your plans, Priya Acharya can help with local context and careful pricing analysis. Schedule a personalized consultation.